| 121 | * ColoState / (project:ColoState356) |
| 122 | * Expected number of students: 50 |
| 123 | * # Assignments: 4 |
| 124 | * First assignment given: mid-January |
| 125 | * Time to do the assignment: 2 weeks |
| 126 | * Machines needed: 50 (one per student) |
| 127 | * Second assignment given: mid March |
| 128 | * Time to do the assignment: 2 weeks |
| 129 | * Machines needed: TBD |
| 130 | * Third assignment given: early April |
| 131 | * Time to do the assignment: 2 weeks |
| 132 | * Machines needed: TBD |
| 133 | * Forth assignment given: end of April |
| 134 | * Time to do the assignment: 2 weeks |
| 135 | * Machines needed: TBD |
| 136 | * Class ends: May 15 |
| 137 | * U Memphis / (project:COMP7327UM) |
| 138 | * Expected number of students: 10 |
| 139 | * # Assignments: 2 |
| 140 | * First assignment given: mid-February |
| 141 | * Time to do the assignment: 2 weeks |
| 142 | * Machines needed: 10 (one per student) |
| 143 | * Second assignment given: mid-March |
| 144 | * Time to do the assignment: 2 weeks |
| 145 | * Machines needed: 10 (1-2 per group) |
| 146 | * Class ends: April 25, 2012 |