| 69 | * YSU (project:YSU-secure) |
| 70 | * Expected number of students: 22 |
| 71 | * # Assignments: 1 |
| 72 | * First assignment given: mid-october |
| 73 | * Time to do the assignment: 1 week (October 31, - November 4) |
| 74 | * Time to do DEMO assignment: 1 week (November 28, - December 2) |
| 75 | * Machines needed: 55 (5 machines per group of two students) |
| 76 | * Class ends: December 16 |
| 77 | * YSU (project:YSU-secure-G) |
| 78 | * Expected number of students: 6 |
| 79 | * # Assignments: 1 |
| 80 | * First assignment given: mid-november |
| 81 | * Time to do assignment: 2 weeks (November 21, - December 2) |
| 82 | * Machines needed: 24 (4 machines per student) |
| 83 | * Class ends: December 16 |