Version 8 (modified by mikeryan, 14 years ago) (diff)

USC

Here is the list of classes along with their info for the next semester:

  • UCLA / UCLAClass
    • # students: 50
    • # machines: Some assignments require 1 machine per student. At least one requires 4. Students do assignments individually.
    • # assignments: 5
    • due dates: These dates aren't firm, but the plan is currently to have assignments due October 8, October 15, October 29, November 5, and November 12.
  • USC / USCCSci530
    • # students: 90 - 120
    • # machines: 3-5 per assignment, depending on the assignment
    • # assignments: 3-4 substansive, 1 initial familiarization
    • due dates: substansive Oct - late Nov, initial mid-September
  • UC Berkeley
  • Vanderbilt University VandyCS285
    • When is class offered: Fall 2010
    • Project name on DETER: VandyCS285
    • Expected number of students: 15
    • # Assignments: 2
    • First assignment given: Nov 1
    • Time to do the assignment: 16 days
    • Machines needed: 50 (at least 3 per student)
    • Second assignment given: Nov 18
    • Time to do the assignment: 3 weeks
    • Machines needed: 80 (8 per group of 4 students)
    • Class ends: Dec 09.
  • Colorado State / ColoState356
    • When is class offered: Fall 2010
    • Project name on DETER: ColoState356
    • Expected number of students: 40
    • # Assignments: 6, roughly every two weeks
    • First assignment given: late-august - this is a warm-up to get accounts and start using DETER
    • Time to do the assignment: 1 week
    • Machines needed: 40 (one per student)
    • Subsequent assignments given: roughly two weeks between assignments
    • Time to do the assignment: 2 weeks
    • Machines needed: 40 (3 per group of 3 students)
    • Class ends: December 17th
  • University of Portland
  • Youngstown State University

This was listed for USC but appears to be inaccurate:

  • USC
    • When is class offered: Fall 2010
    • Project name on DETER: SMC-CS78 (already established)
    • Expected number of students: 25-40
    • # Assignments: 2-4
    • First assignment given: probably September
    • Time to do the assignment: 1 week
    • Machines needed: variable per assignment but more than one per student (3-5) so low/high estimates become 25x3=75 and 40x5=200
    • Subsequent assignments given: spread over Oct-Dec20
    • Time to do each assignment: 1 week
    • Class date range: 8/30/10-12/21/10