2011 Switch Upgrade
ISI
Existing Switches and their replacements.
Cisco4
Current Configuration
Proposed Configuration
- 2x 5412zl chassis
- 2x quad cx4 modules
- 14x gigabit ethernet modules
Nortel10
Current Configuration
- 6x 5510-48T
- 1x 5530-24TFD
Proposed Configuration
- 2x 5412zl chassis
- 2x quad cx4 module
- 13x 24 port gigabit ethernet modules (7 in one chassis, 6 for the other)
Nortel18e
Current Configuration
- 7x 5510-48T
- 1x 5530-24TFD
Proposed Configuration
- 2x 5412zl chassis.
- 2x quad cx4 modules
- 15x 24 port gigabit ethernet modules (8 for one chassis, 6 for the other).
New star switch
one cx4 card per experimental switch.
- 1x 5400zl chassis
- 6x cx4 cards
- 1x x2 card for dragon
Totals
- 7x 5400zl chassis
- 12x cx4 modules
- 42x 24 port gigabit
- 1x X2 module
Parts from HP
Descriptions and Links
- J8702A 24 port gigabit ethernet
- J8705A 20 port gigabit ethernet and 4 mini gbic
- J8707A 4 port 10-Gbe X2 module
- J8708A 4 port CX4 module
- J8437A 10-GbE X2-SC LR
- J8436A 10-GbE X2-SC SR